JavaScript is Required
Accepted Projects Details
Showing Record(s) 1 to 15 of Total 465 Green Box -Projects where all Issues are resolved
S.No Project Name Ministry-Department Description Of Projects
(As furnished by the applicant)
Estimated Investment(in Crores)
1 Shirpur Power Pvt. Ltd.  Power   New Group Captive Power Plant with a capacity of 300 MWs (2x150) at Dhule, Maharashtra for supplying power to group captive consumers. The company has submitted MoU and copies of Board Resolution of captive consumers confirming off-take of more than 51% of power from CPP. The Captive Power Plant is scheduled to be commissioned in March, 2015. Long-Term Linkage is required on urgent basis for the power plant as without linkage the generation of power is not viable in the present circumstances. 1800
2 2 X 50 MW Tidong-I Hydro Electric Project of NSL Tidong Power Generation Pvt Ltd (NTPGPL)  Power   Introduction: 100 MW Tidong I Hydro Electric Project ( HEP) is a run of the river scheme on Tidong Khad, a tributary of river Satluj, located in Kinnaur District of Himachal Pradesh. The project has been allotted to M/s NSL Renewable Power Private Limited (NRPPL) and is being built by its fully owned subsidiary M/s NSL Tidong Power Generation Pvt Ltd, on Built, Operate and Transfer (BOT) basis as a PPP Project for the Government of Himachal Pradesh. Project site falls in 3 Villages namely Lamber, Ruwang and Lizang under Moorang Tehsil of Kinnaur District. The total land required by the project is 42.2557 ha, including 39.0546 ha of forest land and 3.2011 ha of private land. The project will have 2 x 50 MW Vertical Shaft Pelton turbines. The annual energy generation from this project is estimated to be 541.70 MUs in a 90% dependable year. Statutory Clearances: All the necessary Environmental and Forest Clearances for the Main Project are obtained from MoEF, Govt of India and the private land has been acquired for the project under Land Acquisition Act, 1894. After obtaining all statutory clearances, the project construction works started in 2009 and the project is scheduled to commission on 31st July 2016. Given the current progress of the works, the project is expected to be commissioned by Dec 2015. Transmission Lines: As part of the evacuation arrangement, 16.5 km transmission line of 220kV DC capacity is envisaged for evacuation of power from Tidong I HEP to the nearest connecting point at existing Kashang-Bhabah 220 kV DC line. The construction of this line was originally in the scope of Himachal Pradesh Power Tranmission Corporation Limited (HPPTCL) but due to delays in their implementation, M/s Tidong Power Generation Pvt Ltd had taken it into its scope. Project Cost: The estimated cost of the project in the year 2009 at the time of obtaining project approvals is Rs 648 Crores. The financial closure was achieved on 2nd Dec 2010. However due to delays in obtaining approvals for the forest clearance for the transmission lines, the project cost got escalated to Rs 1113 Crores. The financial closure for the cost over runs is in process and expected to be completed by 15th October 2014. There has been substantial delay in sanctioning the loans for the cost over-run funding by existing lenders. This has led to delay in the project implementation due to lack of adequate funding. Still the sanctions are pending with banks/financial institutions. 1113
3 2 X 660 MW Tentulei Thermal Power Project of NSL Nagapatnam Power and Infratech Ltd  Power   1)Capacity : 2x660MW (Super Critical Technology based) 2)Location : Project site falls in the purview of 5 villages namely Tentulei, Ghantapada, Jagannathpur, Sana Scotland and Bada Scotland, all in Angul District, Odisha. 3)Land : Obtained possession of 471 acres, out of total 793 acres. Possession of balance land is in progress & expected to be completed by end Sep 2014. However, the land taken into possession is adequate for main plant works. 4)Fuel : Obtained coal linkage from MCL, MoC/GoI for 70% of the Coal requirement. The project was earlier proposed as Coastal based power project in Tamilnadu state and was allotted only 70% of coal linkage. With due approval from MoC, the project is now shifted to Odisha state and now it is an inland alike pit-head project. 5)Water : Obtained water linkage from Dept of Water Resources (WRD), GoO from Brahmani river. 6)Environmental Clearance: Obtained from Ministry of Environment & Forest (MoEF), Govt. of India (GoI) vide their letter No. J-13012/25/2007-IA.II (T), dated 25.03.2013. 7)Financial Closure: Completed. Common loan Agreement signed on 18-09-2012. 8)Award of EPC contract for entire project : Placed contract award on M/s.Tata Projects Ltd, with BTG awarded to M/s Alstom India limited 7796.78
4 Calcom Cement India Ltd  Commerce and Industry-DIPP  This is a split located Cement project with a capacity of 1.75 million MT of Cement in the first phase. The Limestone mining and Clinkerization project is located in the Dima Hasao District of Assam, while the Grinding project is located in the Naogoan Dist of Assam, at a distance of 70 km where access to Railway Siding and NHAI East-West corridor is available. The Grinding unit at Lanka has been commissioned in August 2010 and is currently being operated with bought out clinker from various plants in and outside the region including a neighboring country. The Clinkerization unit is under construction at Umrangshu and is now expected to be ready for commissioning by November 2014. There has been delays in this project due to various factors like law and order, which has been since resolved, availability of power, infrastructure of Roads, Forest Clearance of Mines etc. Once commissioned this project will have a huge role in supporting the infrastructure projects of National significance under implementation and those projected for the NE region as the project is located in the center of the North-East region and the closest Cement plant to Railway and Road expansion projects as well as Hydroelectricity and Defense projects planned in Arunachal Pradesh. This is in addition a Joint sector project with the Govt. of Assam through the Assam Industrial Development Corporation Ltd. The Dalmia Cement Bharat Ltd is the largest promoter of this project having more than 70 years of Cement manufacturing expertise and this being the only cement project from a National House in the North-East region. 1009
5 102 MW WIND POWER PROJECT  Petroleum and Natural Gas   Brief Project Description: Scope of work includes, in general to, Construction of 102 MW Wind Power Project in Rajasthan on Turnkey basis including Land, Design, Engineering, Supply, Transportation to site, Erection, Commissioning, Associated Civil & Electrical Engineering works, Inter-connections with the State grid, Obtaining all statutory permissions, complete in all respect, comprehensive Operation & Maintenance (O&M) of the Wind Power Project for a period of 10 (TEN) years i.e. 1 (One) year during warranty period from the date of successful commissioning and 9 (Nine) years during post warranty period including all spares, consumables, insurance etc Project Cost: Original Cost 1106 Crore ( Capex 650 & 456 Crore for 20 Year O&M) Approved Cost for Rs 818 Crore( LSTK 650 + 10 year O&M Cost) Awarded Cost Rs 678 Crore ( LSTK 562 + 116 O&M for 10 years) Scheduled Completion as per Board Approval -June 2012. ( 6 months from NOA) Scheduled completion as per contract- 14 months from NOA March-14, Extended up to Oct-14 1106
6 Karimnagar Iron Ore Beneficiation Project  Commerce and Industry-DIPP  Project involves a 10MTPA low grade iron ore mining operation and associated beneficiation plant expected to produce 4MTPA of high grade iron ore. Second phase will involve further value addition through pellet plant. Construction of a local township and associated infrastructure will also be provided in the first stage on investment. 1000
7 Western Onshore Redevelopment Project –Mehsana  Petroleum and Natural Gas   Redevelopment of installations in Mehsana Asset. Total installations covered are 4 installations with 7 pipelines in Group A, 14 Installations in Group B and 8 Installations in Group C. Broad scope covers in general but not limited to Project management, Pre-Engineering site surveys, Residual basic engineering /process design, Detailed Design / Engineering based on process package, Procurement, Supply, Fabrication, Inspection & expediting, Transportation & Delivery of all equipment/materials to the work site, Storage, Site grading & Leveling, dismantling, removal and disposal of scrap & dismantling facilities, Construction (Civil and Structural), Erection / Installation of equipment’s, Piping, Hook up to existing systems, Painting, Insulation, Instrumentation, Electrical Works, Testing, Mechanical Completion, Pre-Commissioning and Commissioning after successful completion of 72 hours continuous Performance Guarantee Test Run (PGTR) for installations. Group-A is under tendering. Group –B & C under pre-tendering. 3823
8 Ahmedabad Asset Redevelopment Project  Petroleum and Natural Gas   The ONGC Board in its 212th meeting, held on 26.11.2010, approved the Redevelopment Plan of Ahmedabad Asset at an estimated cost of Rs. 1916.10 Crores. Ahmedabad Asset Redevelopment Plan includes Revamping of surface facilities & pipelines (surface facilities revamping cost Rs. 932.10 Crores, pipelines Rs. 105.50 Crores) and drilling of development wells as per plan (Rs. 878.50 Crores). The current project, designated as WORP_AMD, is for revamping of surface facilities. The scope of current project covers Revamping of 32 surface installations (GGS, CTF etc.) with an objective to handle increased liquid and cater to various statutory (safety, pollution control, environmental protection etc.) and technical requirements caused due to obsolescence. 1916.1
9 Integrated Steel Plant  Steel   SHLCC in its 14th Meeting held on 17.03.2008 has approved our proposal to setup 2.5 Million Tons Integrated Steel plant along with 250 MW Power Plant with an investment of Rs. 8735.00 Crores in 1201 Acres and 15 Guntas of land at various Sy. Nos. of Kunikere and Hirebagnal villages of Koppal Taluk & District. Our I phase, a 0.8 MTPA Pellet Plant is operational from July, 2011 and awaiting EC for theh II phase, which is pending with MOEF 8735
10 India Power Corporation (Haldia) Limited  Power   3 x 150 MW Thermal Power Project at Haldia with a total investment of Rs 3000 Crore. All necessary clearances have been obtained including Environment Clarence. Required land for the project has already been acquired and main plant equipment has been ordered on BHEL and 40% supply of equipment is received at site. The construction activity is full swing and about 50% civil construction has been completed and erecting of main plant in progress. 3000
11 VANDANA ISPAT LIMITED  Steel   Integrated Steel Plant Project at Village Kopedih /Anjora, Dist. Rajnandgoan, .C.G. Total capaicty of 8.30 LTPA with captive power plant of 120 MW ( 3x40 MW) Major clearance like Environment clearance, consent to Establish etc. obtained. 1310
12 VANDANA VIDHYUT LIMITED  Power   2X135+1X270 Total 540 MW Thermal Power Plant at Village Salora, Tah.Katghora, Dist.Korba C.G. 3700
13 Chandrabila coal block of NTPC  Power   Against the Notice Inviting Application (NIA) dated 31.12.2012, under Rule 4 of the Auction by Competitive Bidding of Coal Mines Rules, 2012, Ministry of Coal on 25.07.13 intimated the decision of Government of India to allocate Chandrabila coal block to NTPC. This coal block is located in Talcher coalfield of Odisha. Detailed exploration in Chandrabila coal block is being carried out for NTPC by CMPDI. Coal from this block is earmarked for Gadarwara-I (1600 MW), Unchahar–IV (500 MW) and Bilhaur-I (1320 MW) Power Projects of NTPC. 1000
14 12 MTPA IRON ORE BENEFICIATION PLANT AT KUMUNDI AND 4 MTPA PELLET PLANT AT JALPAPOSHI WITH IRON ORE SLURRY PIPE LINE FROM JALPAPOSHI , KEONJHAR DISTRICT TO MERAMANDALI ,DHENKANAL DISTRICT OF ODISHA  Steel   The Project consists of 1)12 MTPA Iron Ore Beneficiation Plant at Kumundi, Dist.Keonjhar of Odisha 2) 4 MTPA Pellet Plant at Jalpaposhi 3) 4 MTPA Grinding station at Gandamardan, Keonjhar 4) Iron Ore Slurry Pipe Line from Jalpaposhi to Meramandali -Dhenkanal district ,Steel Plant of Bhushan Steel 1280
15 (6- Laning of Varanasi- Aurangabad section of NH-2 between Km. 786.000 to Km 978.400) in the State of UP and Bihar on DBFOT (PPP) mode  Road Transport and Highways   The work is comprised of 6-Laning of existing 4-Lane highway of NH-2 on DBFOT(PPP) mode. It involves 2 Districts of U.P(Varanasi & Chanduli) and 3 Districts of Bihar(Kaimoor, Rohtas & Aurangabad). There are 3 Toll Plaza locations on this stretch at Km 800 , 860, 907+100 at Varanasi, Mohania and Sasaram locations. 2848
next last
Go to Navigation