JavaScript is Required
Accepted Projects Details
Showing Record(s) 1 to 15 of Total 487 Green Box -Projects where all Issues are resolved
S.No Project Name Ministry-Department Description Of Projects
(As furnished by the applicant)
Estimated Investment(in Crores)
1 Kaniha OCP  Coal   Opencast project of MCL Mode-Both Coal & OB outsourcing Variant. Sanctioned Capacity: 10.00 Mty, Sanctioned Cost: Rs. 457.77 Crore, Date of Sanction: Dec-2007, Sch. date of Completion: Mar-2013, Ant. date of Completion: Mar-2017, 1000
2 Ananta OCP Expn Ph-III  Coal   Open Cast Coal Mine of MCL Incremental OB out sourced for 5 yrs and coal deptt by blast free method. Incremental Capacity: 3 Mty (15.00 Mty total), Date of Sanction: Aug-08, Sanctioned Incremental Cost: Rs. 207.28 Crores. Scheduled date of Completion: March-2012, Ant. date of Completion: March-2017 1000
3 Bharatpur OCP Expn Ph-II & Ph-III  Coal   Opencast project of MCL Ph-II- Contractual variant-330 days a year, Ph-III- Coal out sourcing and incremental OB out sourcing for 5 yrs. PH-II: Capacity: 6.00 Mty, Sanctioned Cost: Rs. 95.87 Crores (incr.), Date sanction: June-03, Sch. date of Completion: Mar-2007, Ant. date of Completion: Mar-2017, PH-III: Capacity: 9.00 MTY Sanctioned cost-Rs 131.39 Crs. Date sanction: Feb-2007, Sch. date of Completion: Mar-2010, Ant. date of Completion: Mar-2017, 1000
4 Jhanjra Continuous Miner 2nd Set.  Coal   Jhanjra Continuous Miner 2nd Set. Sanctioned capacity: 0.51 MTY Sanctioned capital: : Rs.147.25 cr. Sanctioned date : May2011 ( Revised ) 1000
5 Balaram OCP Extension  Coal   Opencast project of MCL Coal & Incre OB by out sourcing and coal by blast free mining Sanctioned Capacity: 8.00 Mty, Sanctioned Cost: Rs. 172.08 Crs., Date of Sanction: Dec-2007, Scheduled date of Completion: Mar-2010, Ant. date of Completion: Mar-17 1000
6 Bhubaneswari OCP  Coal   Opencast Coal Project of MCL Both Coal & OB outsourcing variant Sanc. Capacity: 20.00 Mty, Sanc. capital Rs. 490.10 Crores, Sanction Date: Dec-2007, Sch. Date of Completion: Mar-17, Ant. Date of Completion: Mar-17, 1000
7 Hingula-II OCP Expn Ph-III  Coal   Opencast Coal Project of MCL Incremental OB out sourcing upto 5th yr and coal deptt by surface miner Incremental Capacity: 7 Mty (15.00 Mty total), Date of Sanction: Nov-2008, Sanctioned Incremental Cost: Rs. 479.53 Crs. Scheduled date of Completion: Mar-13, Ant. date of Completion: Mar-17, 1000
8 Jhanjra UG PSLW PH-II  Coal   Jhanjra UG PSLW PH-II Sanctioned Capacity: 1.70 MTY Sanctioned Capital: :Rs.287.17 Crore Sanctioned Date : Nov2006 1000
9 DIPKA OC EXPANSION PROJECT  Coal   Dipka OC Expansion Project (20 to 25 MTY) is an On-going project approved in Dec. 2009 by CIL Board. Total capital outlay is Rs. 1943.66 Crores. Total expenditure incurred till 31st March 2014 is Rs. 1539.323 Crores. The project has already achieved the rated capacity. Construction of In-pit belt conveyor transport system has been completed. Construction of workshop is in progress and expected to be completed by 31st March 2015. EC for 30 MTY (peak capacity under clause 7(ii) of EIA) exists. Additional land required for Expansion PR has been notified u/s 11(i) of CBA Act in two phases. Assessment of compensation is in progress. 1943.66
10 KUSMUNDA OC EXPANSION PROJECT  Coal   Kusmunda OC Expansion Project is an On-going project approved in August 2013 by CIL Board. Total capital outlay is Rs.7612.33 Crores. Total expenditure incurred till 31st March 2014 is Rs.753.418 Crores. Major activities of the project are under implementation at various stages. EC for 18.75 MTY (peak capacity under clause 7(ii) of EIA) exists. Further Form-I for EC for 50 MTY (peak: 62.50 MTY) has already been submitted in June 2014. EAC held on 17.10.14 for issuing TOR. Additional land required for Expansion PR has been notified u/s 4(i) of CBA Act on 13.5.14. Further proposal is being sent to MOC for notification u/s 7(i) of CBA Act. Tendering for construction of 20000 T RCC bunker alongwith its feeding arrangement and 132 kV sub-station is in process. 7612.33
11 GEVRA OC EXPANSION PROJECT  Coal   Gevra OC Expansion Project (25 to 35 MTY) is an On-going project approved in June 2010 by CIL Board. Total capital outlay is Rs. 2675.67 Crores. Total expenditure incurred till 31st March 2014 is Rs. 1532.379 Crores. The project has already achieved the rated capacity. Construction of major infrastructures viz In-pit belt conveyor transport system & Coal handling Plant including Silo are in progress and expected to be commissioned in 2015-16. EC for 40 MTY (peak capacity under clause 7(ii) of EIA) exists. Additional land required for Expansion PR has been notified u/s 11(i) of CBA Act in various phases. Physical possession of land is in progress. In 1st phase, physical possession of two villages namely Pondi & Amgaon is expected to be completed by 31st March 2015. 2675.67
12 Dudhichua Expansion  Coal   Dudhichua Expansion OCP (10 to 15 Mty) was approved by NCL Board on 28/07/2008 with incremental capital of Rs 326.57 crs (integrated capital being Rs 1607.96 crs). The project could not be implemented due to requirement of Forestry Clearance for 443 Ha forest land. 1607.96
13 SIARMAL OCP  Coal   Opencast Coal Project Variant-complete out sourced Sanctioned Capacity: 40.00 Mty (Peak 50.00 Mty), Sanctioned Cost: Rs. 3756.36 Crs, Date sanction: May-14, Sch. date of Completion: Mar-26, 3756.36
14 Sonepur-Bazari (Comb.) OC  Coal   Project Report(PR) for Sonepur Bazari Comb.OC(8.0 MTY) approved by CIL Board on 7th Aug, 2012 in Variant-III option, is an expansion project. Variant-III is a partial outsourcing option i.e. additional load of coal and OB over and above existing departmental capacity is to be outsourced. 1055.05
15 3X660 MW Ghatampur Thermal Power Project  Coal   M/S Neyveli Lignite Corporation Limited signed an MOU with Govt. of UP on 30.10.2010 to set up 3X660 MW Thermal Power Plant in Ghatampur Tehsil of Kanpur Nagar, District in Joint Venture with M/S UP Rajya Vidyut Utapadan Nigam Ltd. Joint Venture Agreement was signed between NlC & UPRVUNL on 06.10.12. The JV Company was formed on 09.11.12. Public Investment Board recommended the project at a estimated cost of Rs. 14375.40 Crores vide F.No. (07)-PF.II/2012 dt. 11.02.2013. Land Acquisition Activities were initiated in November-11 and is nearing completion. 14375
next last
Go to Navigation