JavaScript is Required
Accepted Projects Details
Showing Record(s) 1 to 15 of Total 837 Green Box -Projects where all Issues are resolved
S.No Project Name Ministry-Department Description Of Projects
(As furnished by the applicant)
Estimated Investment(in Crores)
1 Ramanmandi Bahadurgarh Pipeline Capacity Expansion Project  Petroleum and Natural Gas   The project involves capacity expansion of existing Ramanmandi Bahadurgarh multi product Pipeline (RBPL) from existing 4.71 MMTPA to 8 MMTPA by installing additional pumps at Ramanmandi and a new intermediate pumping station at Barwala, Hisar, Haryana). 230
2 Tirupati – Tiruthani – Chennai project  Road Transport and Highways   4-Laning of Tirupati – Tiruthani – Chennai Section of NH-205 for 124.70 Km length on DBFOT under NHDP-III in the state of TN 571
3 Krishnagiri - Walajahpet stretch  Road Transport and Highways   6-Laning of Krishnagiri – Walajahpet section of NH-46 for 148.3 Km length on DBFOT under NHDP –V in the state of TN 1370
4 Eastern System Strengthening Scheme (ERSS) VI  Power   The Project scope consisted the development of following Transmission Infrastructure: 1. Muzaffarpur(PG)- Darbhanga 400 kV D/C line with triple snowbird conductor 2. LILO of Barh –Gorakhpur 400 kV 2xD/C line at Motihari. 3. 2x500 MVA, 400/220 kV Darbhanga GIS with space for future extension 4. 2x500 MVA, 400/132 kV Motihari GIS with space for future extension 1000
5 200 MW Solar Park Project in Kasargod District  New and Renewable Energy  MNRE,GoI through Solar Park scheme will setup 25 solar parks,each with capacity of 500MW and above,thereby targeting 20,000MW of Solar Power capacity within a span of 5 years.The park will provide impetus to solar energy generation by acting as flagship demonstration facility to encourage project develpors & investors,prompting additional projects of same nature,triggering economies of scale for cost reduction,technical improvements & achieving large scale reduction in GHG emissions.GoK has issued orders vide GO No.(MS)15/2015/PD/Tvpm.dtd.27.04.15,for providing land & basic infrastructure facilities for setting up of 200 MW Solar Park at Kasargod Dist.Land had been identified by the Govt,KSEBL has taken over 1086.6579 acres of land on proper yadast & eye sketch on advance possession during July 16.The formal assignment of entire land to KSEBL is awaited from GoK.The implementation of 50MW on behalf of IREDA is progressing at Ambalathara Village,30 MW is targeted to be commissioned by 30.09.2016 & total contracted capacity of 50 MW by 15.12.2016 1200
6 System strengthening in Raipur-Wardha corridor for IPP projects in Chhattisgarh  Power   765 kV (D/C) Raipur-Wardha Line - 712 Ckm 1875.13
7 Ind Barath Energy (Utkal) Limited  Power   IBEUL is setting up 2x350 MW Coal Based TPP (sub-critical) in Sahajbahal in Jharsuguda District, Orissa. COD of Unit I has been achieved on July 20, 2016. 4796.74
8 Barh STPP Stage-I (2X660 MW)  Power   Thermal Power Projects of 1980 MW (3x660 MW ) Barh, Distt.- Patna, Bihar (6km east of Barh town, between NH31 and Patna-Mokama railway line) 15095
9 Delhi - Meerut Expressway  Road Transport and Highways   Delhi - Meetur expressway 5000
10 Visakh Refinery Expansion Evacuation Project, SubSea Jetty Pipeline  Petroleum and Natural Gas   The Project involves the following 1. VVSPL Capacity Expansion with 03 additional pumping stations with associated facilities in existing Visakh Vijayawada Secundrabad Pipeline. 2. Laying of 1.1 km Subsea pipeline with associated facilities for providing pipeline connection from offshore OSTT jetty to onshore SS Jetty. 407
11 Transmission System for Development of Pooling Station in Northern Part of West Bengal and Transfer of Power from Bhutan to NR/WR  Power   POWERGRID is to implement transmission lines and Pooling Sub-Station under the scheme for transfer of Power from Bhutan (approx. 3000 MW) to NR/WR:- 1. LILO of Biswanath Chariali – Agra HVDC Line at New Pooling Station in Alipurduar for parallel operation of the HVDC Station. 2. LILO of Bongaigoan – New Siliguri 400 kV D/C Line (Quad) at New Pooling Station at Alipurduar 3. Punatsangchu–1 (Bhutan) – Alipurduar 400 kV D/C (Indian Portion) 4. LILO of Birpara – Salakati 220 kV D/C Line at New Pooling Station in Alipurduar 5. Earth Electrode line at New Pooling Station in Alipurduar 6. New 2x315MVA, 400/220KV AC & 3000MW ±800KV HVDC Sub-Station at New Pooling Station in Alipurduar. 4404
12 Construction of 20.35km 2- lane Tinsukia bypass with paved shoulders between km 635.80 to 653.40 of NH-37 in Assam SARDP-NE/NH-37/PWD/AS/2009-10/123  Road Transport and Highways   Project was sanctioned on 22.05.2009 by MoRTH with total length for construction of 20.35 km on NH 37 (New NH 15) under the scheme of SARDP-NE Ph A. And 84% work has been completed. 70.71
13 Construction of 2-lane Patherkandi Bypass with paved shoulder (Total length=9.224 km.) under Annual Plan for the year 2014-15 in Karimganj NH Division in the state of Assam. Job No. 044/AS/2014-15/122  Road Transport and Highways   Project was sanctioned on 08.12.2014 with total length for construction of 9.224 km on NH 44. Date of Agreement is 14.08.2015. 74.08
14 MDPL Capacity Expansion & Palanpur Vadodara Pipeline Extension  Petroleum and Natural Gas   This project is for Expansion of System capacity of Mundra Delhi pipeline from existing 5.0 MMTPA to 8.0 MMTPA by installation of additional Pump facilities at Bachau(Gujarat) & Pindwara(Rajasthan) and laying of 235 Km Extension Spur pipeline from Palanpur to proposed Marketing Terminal near Vadodara(Gujarat). 1879
15 Jharkhand Solar Power Projects  New and Renewable Energy  JREDA has conducted competitive bidding of 1200 MW of solar power projects to be set up in the state of Jharkhand. Renew Solar Power was successful in securing 522 MW of solar projects and the LOIs were issued to Renew Solar Power 3100
next last
Go to Navigation